Overview

Vedanta Group is one of the world’s largest global diversified natural resource company with interest in zinc-lead-silver, oil & gas, iron ore, copper, aluminium and commercial power. Vedanta Limited provides metallurgical grade alumina and other high-quality aluminium products to wide range of industries worldwide. Sesa Sterlite Ltd (SSL) is a group company of Vedanta one of the largest manufacturer of aluminium products in India.

Sesa Sterlite Ltd (SSL) was looking for a reliable power solution for “Black start operation” of their Captive thermal power plant (9x135 MW), at Jarsuguda in Odisha. SSL chose Jakson to set up a 36 MVA capacity “Black Start power generating” system for their Captive Power Plant in the year 2012.

Jakson approached SSL as a complete solution provider. We offered complete Design Engineering, Supply, Installation, Testing & Commissioning of a power house consisting of 12 x 3000 KVA 6.6 KV DG sets with all accessories. This is a PLC based SCADA Grid synchronised system offered Start / Stop/AMF operation during power outage. It had capability to manage load & Remote Monitoring of operation etc.

Quick Facts 

  • Client : SSL
  • Project Location : Odisha
  • Capacity : 12 x 3000 KVA 6.6 KV
  • Commissioned Date : 31.03.2014 

 

Business Need

Power is key element for continuous operation of any power plant. Blackout is a total crash of the power grid due to an imbalance between power generation and power consumption. The imbalance of electricity demand & supply can lead to electricity grid crash. In order to avoidBlack start operation” of its Captive thermal power plants, SESA Sterlite Ltd, Odisha required a stable back up power solution providing uninterrupted power. SESA faced on an average 3 to 4 power shut downs each resulting in an approx. 10 crs loss. Our solution offset this loss and enabled a payback to investment within one year. 

Challenges

Some of the challenges faced by the execution team while executing this project related to, a difficult remote site-the nearest city being 300 kms away. This project included development of civil infrastructure adhering to strict quality & safety standards requiring team to stay on-site for long durations. 

Conclusion

  • The project was completed on-time and the solution provided has been to the complete satisfaction of the customer.
  • In order to manage uptime, routine maintenance training has also been provided to the customer to minimise breakdown.
Find out what’s trending in our part of the world

and what we are doing to make a difference. Subscribe to know more.

Become a Dealer

Please fill in the form below and we will contact you shortly.

  • Change the CAPTCHA codeSpeak the CAPTCHA code
     
Business Query
Field icon image missing
Field icon image missing
Field icon image missing
Field icon image missing
Field icon image missing
Field icon image missing
Field icon image missing
Field icon image missing
Field icon image missing
Field icon image missing